NCDOT US-421 & NC-87 Sanford Bypass
Sanford, NC

In 2009 the NCDOT awarded this $27,600,000 project to DHGI through a competitive bid process. This three year project required multiple crews, subcontractors, and seasoned management to deliver the finished product. The 2.3 mile divided 4 lane highway required the excavation and placement of 1,500,000 cubic yards of onsite soils and 200,000 cubic yards of import. There was 29,700 linear feet of pipe installed on this project ranging in size from 4” to 72” in diameter. Forty-five thousand tons of asphalt was placed and 3 bridges were constructed containing over 500 cubic yards of concrete.

Owner/Client:
NCDOT

Project Summary:

2.3 mile divided 4 lane highway
• Placement of 1,500,000 cyds of onsite soils and 200,000 cyds of import.
• 29,700 LF pipe from 4" to 72"

Project Completed:
July 2009 - April 2013