Marcus Stubbs Tower Demolition: D.H. GRIFFIN's Successful Implosion and Abatement in Savannah, GA

marcus stubbs tower

Marcus Stubbs Tower Abatement and Demolition
Savannah, GA

D.H. Griffin was contracted to perform the asbestos removal and demolition of this 15-story apartment building in Savannah, GA. The 185,000 square foot project included asbestos abatement, Universal Waste removal, successful implosion, cleanup, site restoration and erosion control, backfill, grading and seeding. 

Owner/Client:
Housing Authority of Savannah

Project Summary:

Abatement and demolition of over 185,000 sf
• Work included Universal Waste removal
• 15-story building successfully imploded

Project Schedule:
Aug 2007 - Feb 2008