DARI Richmond was selected as the selective demolition subcontractor for the Elevance Health (formerly Anthem) second and third floor restack project in Richmond, VA. The project was a relative breakthrough for DARI Richmond with a newer client in HITT Contracting. DARI was tasked with removing all interior finishes back to the structure while protecting the raised floor system that was to remain. The project had its challenges as the project schedule only allowed six weeks and the General Contractor was unable to get the material hoist erected for three weeks after our start date. Our team shined as they formulated a plan to start on time, work safely while staging demolished materials in an orderly fashion, and keep the necessary production rates to keep the job on schedule for the client. The DARI team successfully completed the 90,000 square foot project on time and under budget.