Project | Clara Cox Homes

demolition of clara cox homes

Asbestos Abatement and Demolition of Clara Cox Homes

High Point, NC

D. H. Griffin Wrecking Co., Inc. was contracted to perform the asbestos removal and complete demolition of 44 multi family public housing units, a community center and day care center in High Point, NC. The asbestos removal included piping insulation, surfacing materials and over 155,000 sf of floor covering. Over 200,000 sf of buildings were demolished utilizing conventional demolition methods.

Owner/Client:
The Housing Authority of High Point

Project Summary:

  • Asbestos abatement and demolition of over 200,000 sf including 44 housing units, a community center building and a day care center building.
  • Work included rough grading and seeding the area.

Project Completed:
May - Sept 2005

 

Return to Listing

Click for the BBB Business Review of this Demolition Contractors in Greensboro NC
Information
  • D.H. Griffin Companies
  • 4716 Hilltop Rd.
  • Greensboro, NC 27407
  • 888-336-3366
Shaping America's Skyline
Contact Us
* *
I'm Contacting You About
* Comments
Required Fields*
 
Copyright © 2017 D.H. Griffin. All rights reserved. Website Development by Beacon Technologies, Inc.